Forgot the RACI? Forget success.

Originally published in March 2024. Updated in November 2026.

I’ve seen it happen more than once, for example on an international project with several external suppliers. At some point, someone asks who was supposed to do that again. By then, the damage is usually done.

Why projects drift

The project runs at full speed, and gradually discussions arise about specific activities. What seems logical to one team or supplier makes no sense to another. The result is a lot of back and forth, and nobody taking ownership.

Some disagreement is inevitable. But in my experience, most of it traces back to agreements that were never made before execution started. Clear roles and responsibilities, agreed upfront, save you a lot of trouble later.

Four letters, one owner

A RACI matrix maps every project activity to the people involved. Responsible is who does the work. Accountable is the single person who owns the outcome. Consulted are the experts who give input before a decision. Informed are the people who need to know what happened.

The golden rule is one A per activity. Two accountable people means nobody is.

Some teams extend the model to RASCI by adding an S for Supportive. These are the parties who help the R (Responsible) during execution, such as a supplier’s engineer or a colleague from another team, without owning the result. Useful, as long as it doesn’t blur who carries the responsibility.

How to build one

Don’t start with names. Start by making the known scope and deliverables explicit. Then break each deliverable down into the work it involves and the expertise it needs, whether that comes from architecture, the technical teams, the business, operations or suppliers. Starting from the deliverables keeps the list complete and prevents it from turning into an org chart.

The result is a list of deliverables, the roles they require and the people who will fill them. Then bring those people together in a workshop to assign the letters and refine them, mapping and validating every activity per project phase, from initiation and planning to execution and closing. Working phase by phase keeps a long list manageable.

Activity
Sponsor
PM
Architect
Technical team
Supplier A
Business
Initiation
Business case and prerequisites
A
R
C
 
 
C
Kick-off
I
R/A
C
I
I
I
Planning
Project plan and milestones
C
R/A
C
C
C
I
High-level design
I
A
R
C
C
C
Execution
Implementation
 
A
C
R
R
I
Acceptance testing
I
A
C
R
C
R
Closing
Documentation
 
A
R
R
R
I
Knowledge transfer and handover
I
A
C
R
R
I
Project sign-off
A
R
I
I
I
C

Example RACI for an infrastructure project. One A per row.

After the workshop, review the draft with the core team, adjust it and ask for formal sign-off. In my projects, a short, high-level version always goes into the kick-off, so everyone starts with the same picture.

A RACI is not a document you file and forget. Scope changes, people change, suppliers come and go. Revisit it at every major milestone.

Drawing up a RACI takes an afternoon. Untangling a dispute about ownership halfway through a project can take weeks. Which would you rather spend your time on?